<address id="jthxv"><listing id="jthxv"><listing id="jthxv"></listing></listing></address>

    <address id="jthxv"></address>

    <address id="jthxv"></address>
    <address id="jthxv"></address>
    <address id="jthxv"><listing id="jthxv"><menuitem id="jthxv"></menuitem></listing></address>
      <noframes id="jthxv"><address id="jthxv"><listing id="jthxv"></listing></address><noframes id="jthxv">
      <address id="jthxv"><address id="jthxv"><listing id="jthxv"></listing></address></address>

      Installation and Debugging

      Home > After-sale Service > Installation and Debugging

      Installingand debugging

       

       

      Executive standard

      GB50116-2013 < Automatic fire alarmsystem design specifications>

      GB50166-2007 <Construction andacceptance normative implementation>

      GB50370-2005 <gas fire extinguishingsystem design standard>

      GB50263-2007 <gas fire extinguishingconstruction and acceptance normative implementation>

       

      Servicecontent

      Gas fire extinguishing debugging

      1. single machine commisioning: Probe testing, alarm devicetesting, delay start time test, the electromagnetic valve of testing

      2. Joint commisioning: debugging with FAS system, automatic fire alarm status,and the choice of valve movements, gas discharge signal feedback Ventilationsystem closed, the fire power to cut off the function debugging, each signalfeedback control center.

       

      Alarm system debugging

      1. single machine commisioning:Fire detector, manual alarm button, sound and light alarm, floor indicatordebugging

      2. joint commisioning:According to the correlation,automatic fire extinguishing system, indoor and outdoor fire hydrant system,smoke exhaust and ventilation air conditioning system, fire doors and activitytype fire separation facilities, fire emergency lighting and evacuationindicating marking system, fire control communication equipment and fireemergency broadcasting system, fire control power supply and distributionsystem, fire water supply system, fire extinguisher joint tests, each signalfeedback control center.

       

      Automaticsprinkler system

      1. single machine debugging: end water-testing device、water-flow indicator、wet alarmvalve, single pump operation, main/standby pump test.

      2. joint commissioning: joint with fire alarm system, through the waterat the end, the flow indicator alarm, wet alarm valve pressure switch alarm,realize the linkage to start the spray pump, each signal feedback controlcenter.

       

      Indoor and outdoor fire hydrant systemdebugging

      1. single machine debugging: Firehydrant button action test running, fire hydrant, fire hydrant pump singlemain/standby pump running debugging.

      2. joint commissioning: linkedwith fire alarm system ,start fire hydrant pump through the fire hydrant buttonand each signal feedback control center

       

      Smokeexhaust&ventilation and air conditioner system

      1. single machine debugging: smokeexhaust valve, air supply valve test, fire valve test, smoke fan operationcommissioning, tuyere wind speed test.

      2. commissioning debugging: startwith fire alarming system, according to the joint program, through the firedetector, manual alarm button alarm signal, smoke control valve, jointly startcorresponding smoke exhaust fan, the signal feedback control center.Smoke fanoperation commissioning, tuyere wind speed test.


      Firedoor and activity type fire separation facilities debugging

      1.  single machine debugging: By manual lifting on either side of the fire shutter buttonaction make fire shutter running up and down and up and down limit accurately

      2. commisioningdebugging:jointwith fire alarm system.  According to thejoint program, it triggers the smoke temperature detector, on either side ofthe fire shutter as fire shutter fire compartmentation, once fell to theground; Asthe fire shutter on the evacuation passageway two drops, smoke alarm, the firstdrop of 1.8 M, temperature sense of alarm, the second fell to the ground, thesignal feedback control center

       

      Fire emergency lighting and evacuation indicating systemdebugging

      1. single machine debugging: evacuation instructions logoshould keep on normally;Fire emergency lightingin open automatically when the power is lighting;

      2. commisioning debugging: Jointwith fire alarming system, according to the joint program, through the firedetector, manual alarm button alarm linkage fire cut off the power supply, fireemergency lighting open lighting system automatically. 

       

      The fire emergency broadcasting system debugging

      1. singleemergency: to check each fire radio voice situation step by step through fireemergency radio host signal accident radio voice.

      2. commissioningdebugging:to checkeach fire radio voice situation step by step Through fire emergency radio hostsignal accident radio voice and fire alarm system, according to the jointprogram, the ground floor and second floor above the alarm, the locking layerand adjacent to the lower level radio open;Alayer of alarm, the locking layer, layer and underground layer accident radioopen;Anyfloor underground alarm and linkage broadcast on each layer and a layer ofunderground accidents..

      執行標準

      GB50116-2

      013 《火災自動報警系統設計規范》

      GB50166-2007 《火災自動報警系統施工及驗收規范》

      GB50370-2005 《氣體滅火系統設計規范》

      GB50263-2007《氣體滅火系統施工及驗收規范》

       

      服務內容

      氣體滅火系統調試

      1. 單機調試:探測器測試、警報裝置測試、延時啟動時間測試、電磁閥動作測試。

      2. 聯合調試:與FAS系統的火警、手自動狀態、選擇閥動作、氣體噴放信號的反饋調試;通風系統關閉,非消防電源切斷功能調試,各信號反饋消控中心。

       報警系統調試

      1. 單機調試:火災探測器、手動報警按鈕、聲光報警器、樓層顯示器調試。

      2. 聯合調試:根據聯動關系,對自動滅火系統、室內外消火栓系統、防煙排煙與通風空調系統、防火門及活動式防火分隔設施、火災應急照明和疏散指示標志系統、消防通訊設備及火災應急廣播系統、消防供電和配電系統、消防供水系統、消防滅火器的聯合測試,各信號反饋消控中心。

       自動噴淋系統調試

      1. 單機調試:末端試水裝置、水流指示器、濕式報警閥,水泵單機運行,水泵主備用切換測試。

      2. 聯合調試:與火災報警系統聯動,通過末端放水、水流指示器報警、濕式報警閥壓力開關報警,實現噴淋泵聯動啟動,各信號反饋消控中心。

       室內外消火栓系統調試

      1. 單機調試:消火栓按鈕動作測試、消火栓泵單機運行、消火栓泵主備用切換運行調試。

      2. 聯合調試:與火災報警系統聯動,通過消火栓按鈕實現消火栓泵聯動啟動,各信號反饋消控中心。

      防煙排煙與通風空調系統

      1. 單機調試:排煙閥、送風閥動作測試,防火閥動作測試,防排煙風機運行調試,風口風速測試。

      2. 聯合調試:與火災報警系統聯動,根據聯動程序,通過火災探測器、手動報警按鈕報警信號,聯動開啟防排煙閥,聯動啟動相應防排煙風機,各信號反饋消控中心。

      防火門及活動式防火分隔設施調試

      1. 單機調試:通過防火卷簾門兩側的手動升降按鈕操作使防火卷簾門上下運行正常且上下限位準確。

      2. 聯合調試:與火災報警系統聯動,根據聯動程序,觸發防火卷簾門兩側的煙溫感探測器,作為防火分隔的防火卷簾門,一次下降至地面;作為疏散通道上的防火卷簾門分兩次下降,煙感報警,第一次下降1.8M,溫感報警,第二次下降至地面,各信號反饋消控中心。

       火災應急照明和疏散指示標志系統調試

      1. 單機調試:疏散指示標志應保持常亮;火災應急照明在斷電后自動開啟照明;

      2. 聯合調試:與火災報警系統聯動,根據聯動程序,通過火災探測器、手動報警按鈕報警信號聯動切斷非消防電源時,火災應急照明系統自動開啟照明。

       火災應急廣播系統調試

      1. 單機調試:通過火災應急廣播主機發出事故廣播語音信號,逐層檢查每個消防廣播的發聲情況。

      2. 聯合調試:與火災報警系統聯動,根據聯動程序,地上二層及二層以上報警,聯動本層及相鄰上下層事故廣播開啟;一層報警,聯動本層、二層及地下各層事故廣播開啟;地下任意層報警,聯動地下各層及一層事故廣播開啟。

       

      Contact

      Us

      日韩激情无码一级毛片软件,9在线无码成人毛片视频免费,A级毛片无码免费真人久久久,亚洲高清AⅤ毛片 (function(){ var bp = document.createElement('script'); var curProtocol = window.location.protocol.split(':')[0]; if (curProtocol === 'https') { bp.src = 'https://zz.bdstatic.com/linksubmit/push.js'; } else { bp.src = 'http://push.zhanzhang.baidu.com/push.js'; } var s = document.getElementsByTagName("script")[0]; s.parentNode.insertBefore(bp, s); })();